| Record | Stage | Operator | Location | Architecture | Suppliers | Capacity | Rack density | Compute | Announced | Fields addressed | Evidence | Sources | Reviewed | Comparison |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Madhya Pradesh–Submer AI capacity program | Planned | Government of Madhya Pradesh and Submer | Madhya Pradesh, India | Direct To Chip, Single Phase Immersion +1 | 1 | Up to 1 GW under a memorandum of understanding | Not disclosed | AI-ready data centers | 2025-07-28 | 9/9 | Supplier reported | 1 |
| Submer Barcelona AI data center | Planned | Submer | Barcelona, Spain | Direct To Chip, Single Phase Immersion +1 | 1 | 56 MW | 150 kW+ per rack or tank (design target) | AI infrastructure | 2025-02-28 | 9/9 | Supplier reported | 1 |
|---|
| LiquidStack 300 MW U.S. multi-site order | Deploying | Undisclosed U.S. data-center operator | Multiple sites, United States | Direct To Chip, Hybrid Cooling | 1 | 300 MW aggregate CDU capacity | Not disclosed | AI-ready, high-density infrastructure | 2025-01-06 | 9/9 | Supplier reported | 1 |
|---|
| NorthC Eindhoven MIXIT chip-cooling loop | Operating | NorthC Datacenters | Eindhoven, North Brabant, Netherlands | Direct To Chip, Heat Reuse +1 | 1 | Not publicly disclosed | Not publicly disclosed | High-performance computing and chip-level liquid-cooled workloads | 2022-06-01 | 9/9 | Supplier reported | 2 |
|---|
| Fugaku Stäubli CGD cooling connections | Operating | RIKEN | Kobe, Hyogo, Japan | Direct To Chip | 1 | 400 racks; compute power capacity not stated in cited cooling source | Not publicly disclosed | Fujitsu Fugaku supercomputer with more than 150,000 processors reported by Stäubli | 2021-03-09 | 9/9 | Supplier reported | 2 |
|---|
| NREL ESIF warm-water cooling loop | Operating | National Renewable Energy Laboratory | Golden, Colorado, United States | Direct To Chip, Heat Reuse +1 | 2 | IT capacity not disclosed in the cited Xylem case | Not disclosed | Warm-water liquid-cooled high-performance computing systems | 2012-01-01 | 9/9 | Operating evidence | 2 |
|---|